The operating plan for a multi-day company conference, from the six-month mark to the close-out report.
On this page5 parts
The timeline
Milestones, working backwards.
Dates are relative to the event. Anything that has slipped past its marker here is not automatically lost, but it is no longer free — and the honest conversation is better had now than in the final fortnight.
T-6 months
Objective agreed, decision rights named, venue contracted, hotel block secured with the cut-off in the calendar
T-4 months
Agenda architecture against the floorplan, group air sourced, sponsorship inventory defined
T-3 months
Registration open, visas started, production design locked, speaker list confirmed
T-6 weeks
Rooming list first pass, transfer plan by arrival wave, exhibitor and sponsor deadlines closed
T-3 weeks
Content locked, run of show issued, technical rehearsal scheduled, escalation matrix published
T-1 week
Final numbers to venue, badge print run, briefing packs issued, contingency reviewed
On site
Morning briefing, live desk, evening handover, written incident log
T+2 weeks
Master bill reconciled, data exported, debrief held, carry-forward list written
The principles
What this format rewards.
The agenda decides the floorplan
Build the agenda against the building, not against a blank page. How many rooms, at what set, with what turnaround, and can nine hundred people get coffee in twenty minutes without missing the keynote.
Staff arrivals against the peak wave
Six hundred delegates arrive in four clusters. Transfers, hotel check-in and registration staffed for the largest wave, with a staffed exception desk beside the scan lanes.
One content desk, locked at T-3 weeks
Every deck to one place, version controlled, checked on the show system, and locked. Speakers who want changes talk to the content desk, not a technician at a coffee break.
The evening is part of the programme
Awards and the social night carry as much of the message as the keynote. Script them, light them, rehearse them and agree the banqueting sequence with the venue.
Other playbooks
Different format, same discipline.
That is the plan. We can also be the ones running it.
Every milestone above has an owner, a date and a consequence for missing it. If you would rather that owner was us, send the format, the dates and the headcount.